{"id":35528,"date":"2025-10-06T09:10:25","date_gmt":"2025-10-06T07:10:25","guid":{"rendered":"https:\/\/www.adriaports.com\/uncategorized\/koper-divaca-second-track-almost-10-kilometres-laid\/"},"modified":"2025-10-12T09:11:11","modified_gmt":"2025-10-12T07:11:11","slug":"koper-divaca-second-track-almost-10-kilometres-laid","status":"publish","type":"post","link":"https:\/\/www.adriaports.com\/en\/railways\/koper-divaca-second-track-almost-10-kilometres-laid\/","title":{"rendered":"Koper\u2013Diva\u010da second track: almost 10 kilometres laid"},"content":{"rendered":"<p><strong>TRIESTE \u2013<\/strong> Along the 27-kilometre route of the new <strong>second railway track between the Port of Koper and Diva\u010da, nearly 10 kilometres of rails have already been laid.<\/strong><\/p>\n<p>Following the completion last July of the main civil works on the section between \u010crni Kal and Koper, work is now progressing rapidly on track laying \u2014 which, in some areas, runs in parallel with the final construction activities to speed up completion.<br \/>\nAccording to <a href=\"https:\/\/drugitir.si\/en\" target=\"_blank\" rel=\"noopener\">2TDK<\/a>, the state-owned company leading the project, <strong>the line will be ready for the first technical tests by March 2026<\/strong>, running from Diva\u010da to Koper. This is despite the challenges posed by the karst terrain and landslides in the Glin\u0161\u010dica Valley (Val Rosandra on the Slovenian side). Complex slope-stabilisation works are underway there, involving geologists and engineers to ensure long-term safety. Inside the tunnels, <a href=\"https:\/\/www.adriaports.com\/it\/ferrovie\/ferrovia-capodistria-divaccia-necessari-ponti-nelle-grotte-carsiche\/\">five viaducts are being completed<\/a>, built under particularly demanding logistical conditions due to the large karst cavities encountered along the route.<\/p>\n<p>Despite technical challenges and inflation, the project continues to remain within the budget set in 2019 \u2014 a result that 2TDK describes as a source of pride in a context of rising material and labour costs.<br \/>\nFurther confirmation of sound project management comes from a <strong>recent audit conducted by CINEA, the European Climate, Infrastructure and Environment Executive Agency<\/strong>, which oversees funds from the Connecting Europe Facility (CEF) programme. <strong>The review, focused on tunnel-related expenses for sections T1\u2013T7 between 2018 and 2022 (\u20ac79.6 million), found no irregularities and made no recommendations.<\/strong> Procurement contracts, accounting accuracy and payment traceability were all verified with positive results.<\/p>\n<p>2TDK\u2019s management welcomed the outcome, calling it <strong>\u201ca confirmation of our meticulous work in line with the highest project management standards, strengthening public and European partners\u2019 confidence.\u201d<\/strong><\/p>\n","protected":false},"excerpt":{"rendered":"<p>TRIESTE \u2013 Along the 27-kilometre route of the new second railway track between the Port of Koper and Diva\u010da, nearly 10 kilometres of rails have already been laid.<\/p>\n","protected":false},"author":2,"featured_media":33546,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_et_pb_use_builder":"","_et_pb_old_content":"","_et_gb_content_width":"","footnotes":""},"categories":[25,37],"tags":[],"class_list":["post-35528","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-logistics","category-railways","et-has-post-format-content","et_post_format-et-post-format-standard"],"yoast_head":"\n<title>Koper\u2013Diva\u010da second track: almost 10 kilometres laid - AdriaPorts<\/title>\n<meta name=\"description\" content=\"Project remains within 2019 budget limits. CINEA audit confirms proper management and EU fund use\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/www.adriaports.com\/en\/railways\/koper-divaca-second-track-almost-10-kilometres-laid\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Koper\u2013Diva\u010da second track: almost 10 kilometres laid - AdriaPorts\" \/>\n<meta property=\"og:description\" content=\"Project remains within 2019 budget limits. CINEA audit confirms proper management and EU fund use\" \/>\n<meta property=\"og:url\" content=\"https:\/\/www.adriaports.com\/en\/railways\/koper-divaca-second-track-almost-10-kilometres-laid\/\" \/>\n<meta property=\"og:site_name\" content=\"AdriaPorts\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/AdriaPortsShipping\" \/>\n<meta property=\"article:published_time\" content=\"2025-10-06T07:10:25+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2025-10-12T07:11:11+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/www.adriaports.com\/wp-content\/uploads\/2025\/04\/KP-Divaccia-4-2025.jpg\" \/>\n\t<meta property=\"og:image:width\" content=\"1500\" \/>\n\t<meta property=\"og:image:height\" content=\"1125\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/jpeg\" \/>\n<meta name=\"author\" content=\"Riccardo Coretti\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Riccardo Coretti\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"2 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/railways\\\/koper-divaca-second-track-almost-10-kilometres-laid\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/railways\\\/koper-divaca-second-track-almost-10-kilometres-laid\\\/\"},\"author\":{\"name\":\"Riccardo Coretti\",\"@id\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/#\\\/schema\\\/person\\\/e1f4a3e4ab6a5399d77daa3fcfd7e9a4\"},\"headline\":\"Koper\u2013Diva\u010da second track: almost 10 kilometres laid\",\"datePublished\":\"2025-10-06T07:10:25+00:00\",\"dateModified\":\"2025-10-12T07:11:11+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/railways\\\/koper-divaca-second-track-almost-10-kilometres-laid\\\/\"},\"wordCount\":292,\"publisher\":{\"@id\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/#organization\"},\"image\":{\"@id\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/railways\\\/koper-divaca-second-track-almost-10-kilometres-laid\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/www.adriaports.com\\\/wp-content\\\/uploads\\\/2025\\\/04\\\/KP-Divaccia-4-2025.jpg\",\"articleSection\":[\"Logistics\",\"Railways\"],\"inLanguage\":\"en-US\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/railways\\\/koper-divaca-second-track-almost-10-kilometres-laid\\\/\",\"url\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/railways\\\/koper-divaca-second-track-almost-10-kilometres-laid\\\/\",\"name\":\"Koper\u2013Diva\u010da second track: almost 10 kilometres laid - AdriaPorts\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/railways\\\/koper-divaca-second-track-almost-10-kilometres-laid\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/railways\\\/koper-divaca-second-track-almost-10-kilometres-laid\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/www.adriaports.com\\\/wp-content\\\/uploads\\\/2025\\\/04\\\/KP-Divaccia-4-2025.jpg\",\"datePublished\":\"2025-10-06T07:10:25+00:00\",\"dateModified\":\"2025-10-12T07:11:11+00:00\",\"description\":\"Project remains within 2019 budget limits. CINEA audit confirms proper management and EU fund use\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/railways\\\/koper-divaca-second-track-almost-10-kilometres-laid\\\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/www.adriaports.com\\\/en\\\/railways\\\/koper-divaca-second-track-almost-10-kilometres-laid\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/railways\\\/koper-divaca-second-track-almost-10-kilometres-laid\\\/#primaryimage\",\"url\":\"https:\\\/\\\/www.adriaports.com\\\/wp-content\\\/uploads\\\/2025\\\/04\\\/KP-Divaccia-4-2025.jpg\",\"contentUrl\":\"https:\\\/\\\/www.adriaports.com\\\/wp-content\\\/uploads\\\/2025\\\/04\\\/KP-Divaccia-4-2025.jpg\",\"width\":1500,\"height\":1125,\"caption\":\"An image of works along the new railway between Koper and Diva\u010da.\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/railways\\\/koper-divaca-second-track-almost-10-kilometres-laid\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Koper\u2013Diva\u010da second track: almost 10 kilometres laid\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/#website\",\"url\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/\",\"name\":\"AdriaPorts\",\"description\":\"AdriaPorts \u00e8 la principale fonte di notizie su Porti, Logistica, Ferrovie e Cantieri Navali del Nord Adriatico\",\"publisher\":{\"@id\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/#organization\",\"name\":\"AdriaPorts\",\"url\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/#\\\/schema\\\/logo\\\/image\\\/\",\"url\":\"https:\\\/\\\/www.adriaports.com\\\/wp-content\\\/uploads\\\/2021\\\/06\\\/logo.svg\",\"contentUrl\":\"https:\\\/\\\/www.adriaports.com\\\/wp-content\\\/uploads\\\/2021\\\/06\\\/logo.svg\",\"width\":678,\"height\":119,\"caption\":\"AdriaPorts\"},\"image\":{\"@id\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/#\\\/schema\\\/logo\\\/image\\\/\"},\"sameAs\":[\"https:\\\/\\\/www.facebook.com\\\/AdriaPortsShipping\",\"https:\\\/\\\/www.linkedin.com\\\/company\\\/adriaports\\\/\",\"https:\\\/\\\/t.me\\\/adriaports\"]},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/#\\\/schema\\\/person\\\/e1f4a3e4ab6a5399d77daa3fcfd7e9a4\",\"name\":\"Riccardo Coretti\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/af80fe5463f86bb046a71d217f7b5541ae6893d2ac1f5850b850a97dfaaf061e?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/af80fe5463f86bb046a71d217f7b5541ae6893d2ac1f5850b850a97dfaaf061e?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/af80fe5463f86bb046a71d217f7b5541ae6893d2ac1f5850b850a97dfaaf061e?s=96&d=mm&r=g\",\"caption\":\"Riccardo Coretti\"},\"url\":\"https:\\\/\\\/www.adriaports.com\\\/en\\\/author\\\/riccardo\\\/\"}]}<\/script>\n","yoast_head_json":{"title":"Koper\u2013Diva\u010da second track: almost 10 kilometres laid - AdriaPorts","description":"Project remains within 2019 budget limits. CINEA audit confirms proper management and EU fund use","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/www.adriaports.com\/en\/railways\/koper-divaca-second-track-almost-10-kilometres-laid\/","og_locale":"en_US","og_type":"article","og_title":"Koper\u2013Diva\u010da second track: almost 10 kilometres laid - AdriaPorts","og_description":"Project remains within 2019 budget limits. CINEA audit confirms proper management and EU fund use","og_url":"https:\/\/www.adriaports.com\/en\/railways\/koper-divaca-second-track-almost-10-kilometres-laid\/","og_site_name":"AdriaPorts","article_publisher":"https:\/\/www.facebook.com\/AdriaPortsShipping","article_published_time":"2025-10-06T07:10:25+00:00","article_modified_time":"2025-10-12T07:11:11+00:00","og_image":[{"width":1500,"height":1125,"url":"https:\/\/www.adriaports.com\/wp-content\/uploads\/2025\/04\/KP-Divaccia-4-2025.jpg","type":"image\/jpeg"}],"author":"Riccardo Coretti","twitter_card":"summary_large_image","twitter_misc":{"Written by":"Riccardo Coretti","Est. reading time":"2 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/www.adriaports.com\/en\/railways\/koper-divaca-second-track-almost-10-kilometres-laid\/#article","isPartOf":{"@id":"https:\/\/www.adriaports.com\/en\/railways\/koper-divaca-second-track-almost-10-kilometres-laid\/"},"author":{"name":"Riccardo Coretti","@id":"https:\/\/www.adriaports.com\/en\/#\/schema\/person\/e1f4a3e4ab6a5399d77daa3fcfd7e9a4"},"headline":"Koper\u2013Diva\u010da second track: almost 10 kilometres laid","datePublished":"2025-10-06T07:10:25+00:00","dateModified":"2025-10-12T07:11:11+00:00","mainEntityOfPage":{"@id":"https:\/\/www.adriaports.com\/en\/railways\/koper-divaca-second-track-almost-10-kilometres-laid\/"},"wordCount":292,"publisher":{"@id":"https:\/\/www.adriaports.com\/en\/#organization"},"image":{"@id":"https:\/\/www.adriaports.com\/en\/railways\/koper-divaca-second-track-almost-10-kilometres-laid\/#primaryimage"},"thumbnailUrl":"https:\/\/www.adriaports.com\/wp-content\/uploads\/2025\/04\/KP-Divaccia-4-2025.jpg","articleSection":["Logistics","Railways"],"inLanguage":"en-US"},{"@type":"WebPage","@id":"https:\/\/www.adriaports.com\/en\/railways\/koper-divaca-second-track-almost-10-kilometres-laid\/","url":"https:\/\/www.adriaports.com\/en\/railways\/koper-divaca-second-track-almost-10-kilometres-laid\/","name":"Koper\u2013Diva\u010da second track: almost 10 kilometres laid - AdriaPorts","isPartOf":{"@id":"https:\/\/www.adriaports.com\/en\/#website"},"primaryImageOfPage":{"@id":"https:\/\/www.adriaports.com\/en\/railways\/koper-divaca-second-track-almost-10-kilometres-laid\/#primaryimage"},"image":{"@id":"https:\/\/www.adriaports.com\/en\/railways\/koper-divaca-second-track-almost-10-kilometres-laid\/#primaryimage"},"thumbnailUrl":"https:\/\/www.adriaports.com\/wp-content\/uploads\/2025\/04\/KP-Divaccia-4-2025.jpg","datePublished":"2025-10-06T07:10:25+00:00","dateModified":"2025-10-12T07:11:11+00:00","description":"Project remains within 2019 budget limits. CINEA audit confirms proper management and EU fund use","breadcrumb":{"@id":"https:\/\/www.adriaports.com\/en\/railways\/koper-divaca-second-track-almost-10-kilometres-laid\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/www.adriaports.com\/en\/railways\/koper-divaca-second-track-almost-10-kilometres-laid\/"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.adriaports.com\/en\/railways\/koper-divaca-second-track-almost-10-kilometres-laid\/#primaryimage","url":"https:\/\/www.adriaports.com\/wp-content\/uploads\/2025\/04\/KP-Divaccia-4-2025.jpg","contentUrl":"https:\/\/www.adriaports.com\/wp-content\/uploads\/2025\/04\/KP-Divaccia-4-2025.jpg","width":1500,"height":1125,"caption":"An image of works along the new railway between Koper and Diva\u010da."},{"@type":"BreadcrumbList","@id":"https:\/\/www.adriaports.com\/en\/railways\/koper-divaca-second-track-almost-10-kilometres-laid\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/www.adriaports.com\/en\/"},{"@type":"ListItem","position":2,"name":"Koper\u2013Diva\u010da second track: almost 10 kilometres laid"}]},{"@type":"WebSite","@id":"https:\/\/www.adriaports.com\/en\/#website","url":"https:\/\/www.adriaports.com\/en\/","name":"AdriaPorts","description":"AdriaPorts \u00e8 la principale fonte di notizie su Porti, Logistica, Ferrovie e Cantieri Navali del Nord Adriatico","publisher":{"@id":"https:\/\/www.adriaports.com\/en\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/www.adriaports.com\/en\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/www.adriaports.com\/en\/#organization","name":"AdriaPorts","url":"https:\/\/www.adriaports.com\/en\/","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/www.adriaports.com\/en\/#\/schema\/logo\/image\/","url":"https:\/\/www.adriaports.com\/wp-content\/uploads\/2021\/06\/logo.svg","contentUrl":"https:\/\/www.adriaports.com\/wp-content\/uploads\/2021\/06\/logo.svg","width":678,"height":119,"caption":"AdriaPorts"},"image":{"@id":"https:\/\/www.adriaports.com\/en\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.facebook.com\/AdriaPortsShipping","https:\/\/www.linkedin.com\/company\/adriaports\/","https:\/\/t.me\/adriaports"]},{"@type":"Person","@id":"https:\/\/www.adriaports.com\/en\/#\/schema\/person\/e1f4a3e4ab6a5399d77daa3fcfd7e9a4","name":"Riccardo Coretti","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/secure.gravatar.com\/avatar\/af80fe5463f86bb046a71d217f7b5541ae6893d2ac1f5850b850a97dfaaf061e?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/af80fe5463f86bb046a71d217f7b5541ae6893d2ac1f5850b850a97dfaaf061e?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/af80fe5463f86bb046a71d217f7b5541ae6893d2ac1f5850b850a97dfaaf061e?s=96&d=mm&r=g","caption":"Riccardo Coretti"},"url":"https:\/\/www.adriaports.com\/en\/author\/riccardo\/"}]}},"_links":{"self":[{"href":"https:\/\/www.adriaports.com\/en\/wp-json\/wp\/v2\/posts\/35528","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.adriaports.com\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.adriaports.com\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.adriaports.com\/en\/wp-json\/wp\/v2\/users\/2"}],"replies":[{"embeddable":true,"href":"https:\/\/www.adriaports.com\/en\/wp-json\/wp\/v2\/comments?post=35528"}],"version-history":[{"count":1,"href":"https:\/\/www.adriaports.com\/en\/wp-json\/wp\/v2\/posts\/35528\/revisions"}],"predecessor-version":[{"id":35529,"href":"https:\/\/www.adriaports.com\/en\/wp-json\/wp\/v2\/posts\/35528\/revisions\/35529"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.adriaports.com\/en\/wp-json\/wp\/v2\/media\/33546"}],"wp:attachment":[{"href":"https:\/\/www.adriaports.com\/en\/wp-json\/wp\/v2\/media?parent=35528"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.adriaports.com\/en\/wp-json\/wp\/v2\/categories?post=35528"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.adriaports.com\/en\/wp-json\/wp\/v2\/tags?post=35528"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}